Which term means the relationships where one task must finish before another starts?

Explore the World Scholar's Cup with our comprehensive test guide. Practice with flashcards and multiple choice questions, each accompanied by hints and explanations. Prepare thoroughly for your academic competitions!

Multiple Choice

Which term means the relationships where one task must finish before another starts?

Explanation:
In scheduling, when one task must finish before another can start, that relationship is called a dependency. It creates an order: the first task completes, then the second can begin. This is specifically the finish-to-start type of dependency, which is the typical way we model prerequisites in a plan and helps determine the project timeline and the critical path. The other terms don’t describe this linking rule—the schedule itself is a harmonogram, the Waterfall method is a project process model, and the Stakhanovite Movement is unrelated historically.

In scheduling, when one task must finish before another can start, that relationship is called a dependency. It creates an order: the first task completes, then the second can begin. This is specifically the finish-to-start type of dependency, which is the typical way we model prerequisites in a plan and helps determine the project timeline and the critical path. The other terms don’t describe this linking rule—the schedule itself is a harmonogram, the Waterfall method is a project process model, and the Stakhanovite Movement is unrelated historically.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy